Section 278 technical approval at Redhill

The cakes were bought in the office, following technical approval being granted by ViaEM to our detailed design of highway works on the A60 Mansfield Road at Redhill in Nottingham. We previously designed the S278 works for Phase 1, the redevelopment of the former Metallifacture site, built by Cora. Cameron Homes have taken on Phase 2, the land to the rear of Phase 1, which requires the current priority controlled junction to be upgraded to traffic signal control. It is a complicated layout, needing to fit in the space reserved in front of Phase 1, on a very busy arterial route in to the centre of Nottingham. Despite that, following our submission, and a first round of comments from ViaEM on 11 December 2025, the technical approval letter was issued only three months later, on 30 March 2026. Well done to our Infrastructure Design team.